The MPS calls for 50 units of Product A and 60 of B. There are currently 25 of Product B on hanD. Each A requires 2 of Part C; each B requires 5 of C. There are 160 units of C available. The net requirements for C are | ERP
The MPS calls for 50 units of Product A and 60 of B. There are currently 25 of Product B on hanD. Each A requires 2 of Part C; each B requires 5 of C. There are 160 units of C available. The net requirements for C are | ERP
A. 115
B. 175
C. 240
D. 690
Ans: A